Monday, May 18, 2009

Final Post

I apologize for the delay to put up the final posting with pictures. We moved into the house towards the end of February and have been unpacking, putting on the finishing touches and receiving all kinds of friends and families! The kids are doing great and love their new home. Its so nice to see them playing in the backyard or in their rooms, it really makes all the work worth it.

Overall the project took around 8 months to complete. It was a really nice feeling making the final payment to the Contractor and having all the headaches behind us. Of course right after I made the final payment it rained and there was a leak above the downstairs bathroom!!! Good thing that my Dad was in town a few weeks later and we were able to find the leak and patch up the damage it caused to the drywall.

Now like all homeowners I just have to mow the lawn and weed the garden. I'm hopefully done with any more big projects for a long time. Now I just need to refinance the house and try to clean up some of the debt I've collected from the remodel. Unfortunately the market here in DC has gone down since last July, so I may not be able to take out to much equity.

Thanks for taking interest in our blog, it's been a lot of fun sharing this experience.










Wednesday, February 4, 2009

Final two weeks?

Well we have officially passed the six month mark.  Nothing yet from the bank, but I'm sure they need some sort of extension soon, since the contractor was supposed to finish in six months.  

The good news is progress is being made and I think we may be able to move in the week of the 16th.  The bad news is we are still waiting to get power and gas connected to the house.  My hope is that tomorrow the gas will be connected and Friday the power will be connected. 

This week, the contractor started applying a couple coats of varnish to the staircase.  He should be finishing it in the next few days.  He also began painting the exterior of the house and has a few more coats to complete that job.

When I arrived at the house tonight I was pleasantly surprised to also find the granite countertops had already been installed.  The granite's color was even correct!  The only problem was that above the dishwasher a electrical outlet and light.




So here is whats left:
Buy appliances and install them(must have working alarm system first)
Finish exterior painting
Touch-up painting inside
Paint front and rear exterior doors
Connect HVAC system (power, gas, thermostat)
Staircase
Drywall small room under staircase
Gutters and Facia Board (rear of house)
Purchase/install 60" vanity mirror upstairs
Install 2 faucets in kitchen (sink and bar sink)
Install tub faucet (upstairs bathroom)
Install shelves in upstairs closet
Fix/Replace broken hindge on island cabinet
Relocate electrical outlet and light switch in kitchen
Install granite backplash over dishwasher
Install water heater


Thursday, January 22, 2009

Tuesday, January 20, 2009

Bathrooms done, now we need power and a kitchen!

Things have been moving along the past week.  Unfortunately last weekend someone broke in and stole several things including the contractors generator and tools.  Even with that setback, the contractor finished the bathrooms and Friday began working on the oak staircase.  During the weekend and various nights I spent time installing the lights and finishing up the alarm system.

 

 

The plan this week will be for the Contractor to finish the staircase and begin on installing the kitchen cabinets.  With the cabinets in place he can have the granite installed. Our BIG challenge this week will be to get the power company to come out and connect the power.  The problem is I had the Contractor move the meter to a corner of the house.  I was given some bad information from a power company representative who basically said we could move the panel since we destroyed the front wall.  Now after I called the power company they are telling me I need to pay a large amount of money to have their crew come out and install a new cable.  The other problem is I do not know how long it will take to get them to complete the work.  Without electricity I cannot complete the alarm and will not be able to purchase any appliances for security reasons.

Thursday, January 8, 2009

Interior doors and more tiling.

  As we only have a few weeks left I figure it's probably time for another posting to show whats been going on. Each night I have been going to the house and verifying that some progress is being made each day. We can't afford any day without some type of progress if we want to finish by the end of the month.

 

During the first part of the week the contractor focused on finishing the bathroom tiling. Overall I am very pleased with their work. Both bathrooms turned out exactly like I had sketched them, so I can't complain.

 

Today the Contractor began installing the interior doors and trim. Nothing really special about the doors. Originally I wanted solid pine doors and the Contractor agreed that he would buy them. But after he realized that solid pine doors were twice as much as what he normally buys, he told me once again that I would have to pay more. I decided this fight wasn't worth it and let him install the standard 6 panel door. I also noticed tonight when I went to the house that they installed the fascia board in the front of the house. The fascia board is basically the only barrier between the outside and my tiny attic space. Thanks to my Dad's suggestions the Contractor installed several air vents along the board.

 

Sunday, January 4, 2009

Paint, floors and tiles!

After a few reminders from a couple of friends I guess it's time to update. For the last month my family and I have been in Peru on vacation. During that time the Contractor was literally waiting for the paint to dry! We chose a off-white color for the walls and a classical white color for the ceiling. Overall I'm pleased with the paint job, a lot of touching-up will have to be done before we move-in but at this stage it looks good.

Once the paint was dry the Contractor began placing the oak flooring. The flooring comes pre-stained and went in pretty fast. When I got back from Peru on Tuesday the flooring was 80% complete, with the kitchen and entryway still left to be completed. Today when I was there they completed the rest.



Yesterday afternoon I received a call from the Contractor stating he wanted $750 additional to tile the bathrooms. Our contract was a little vague, but back in July before the project began, my Father and I confirmed verbally the tile design and he agreed that he would do the job. Now he wanted me to pay more because he said the tile was not standard and required additional work. So once again we had a long fight over the phone and I said he would do the work for free or he was fired. He said his guys would do the work, but I need to pay $250 at least, I said I would not pay anything extra. The conversation basically ended there, but when I arrived at the house this morning the tiling was already 70% complete. I guess he knew his guys had already started and was trying to get something out of me. At this point he knows he must complete the project since all his profit is tied in the completion of the bathrooms and kitchen. As usual he was just being dishonest in order to scrounge a few extra dollars.


Originally we thought the cabinets would be here and ready to install by now. The problem was I decided that I wanted to put some decorative trim on the top and base of the cabinets. I should have known that decorative trim means extra work and in-turn means I would need to pay more. At this point I don't want to pay this SOB anymore money and I will install the trim later on when my Father is back in town. On Monday I will call the cabinet store and cancel the decorative trim in order for the contractor to order the cabinets at no additional cost.

So the plan this week is for his guys to finish all the floors and tiling. Following those items they can install the doors and trim throughout the house. They should also be installing the new gutters and fascia boards.

Thursday, November 27, 2008

Walls at last!

Well after several weeks "inspections" we are back in business. Two laborers showed up at the house last Thursday and began installing drywall. It was about a 2.5 day process for two guys to get 120 pieces of sheet rock up. Then they taped the seems and started putting the putty in to make it all smooth. Because of the cold temperatures here in DC and the fact we have no electricity yet, the house is COLD. So nothing will dry very fast and it could take about two weeks before we are ready for a first coat of paint. Hopefully the painting will be done in three weeks, but who knows.

In the meantime I am trying to get the electrical turned on so we can get space heaters in to speed things along! Since I installed a new service panel on the other side of the front door, the electric company will need to come out to the house and do a bit of work. I'm told that can take several weeks.



Finally on Monday morning, my father went home to Seattle. I was able to talk him in to staying past the Apple Cup, but he drew the line for being home in time for Turkey day. While he was here he did A LOT of work as always. He re-framed the bedroom closet, installed new patio pavers, poured a 16'x20' cement driveway, patched the roof, installed all the insulation, and much more to move the project along. Thanks again Dad!

This weekend my plan is to buy all the faucets, sinks and light fixtures the contractor needs. I'll be leaving for a long vacation next week, so it's really important everything is ready.

Friday, November 7, 2008

Inspection time, week 4??? (my time to vent!)

Well not a lot of progress on the house since the last posting unfortunately. The contractor failed the first plumbing inspection two weeks ago and is now scheduled for his second attempt this coming Wednesday. The electrical inspection passed last Thursday, luckily my father was at the house to let the inspector in. Once the plumbing passes on Wednesday, the contractor will call and schedule for the framing and HVAC inspection to happen. Overall I am extremely concerned at the lack of progress on the part of the Contractor. He did not pass the first inspection and then was unable to schedule a second inspection until I basically did it for him on Wednesday. Of course the Contractor is saying it's the government of DC's fault by not answering their phones and not returning their messages.

The good is my Dad is here and as always is working his tail off. It's been really nice drinking beer with Grandpa at night and talking about everything. The kids and Yeny also love spending time with him. Since he has been here, he has finished installing the gas fireplace, installed the molding on the front of the house (pics soon!), fixed all the lighting locations, and patched the heck out of the roof. The Contractor cuts a big hole in the roof and then expects us to fix the hole since it's not in the contract. Again I know everyone is saying "you get what you pay for!"

Thursday, October 23, 2008

Inspection time

Sorry for the three weeks since the last posting. Since my last posting a good deal has been accomplished, but not as much as we were hoping. The plumbing is now complete. The upstairs bathroom has a shower base and bath tub installed. The contractor did not understand that I wanted to choose every item placed in my house, so he got away with buying a cheap shower faucet and tub. The problem was he payed a plumber to come out and install both, so I would have to pay the plumber to come out and uninstall, and then re-install new materials. In the end, I lost another battle and accepted two mediocre items. From now on the Contractor understands I will choose and probably buy everything that will be installed.
With the plumbing all done the Contractor then moved on to finishing the electrical work. I made sure to stop by every day, so I could talk to the workers and ensure they put all the lights in the correct places and light switches in logical spots. Just a few changes were needed and overall they did an excellent job. The contractor's plan is to do all the work himself and then pay an electrician to come in and inspect the work and put his name on the work. The contractor called me at the beginning of this week to tell me I had to buy the wire to connect the new circuit breaker to the meter outside. After several arguments I caved again and agreed to pay about $75 to $150 to get the electrical system completed and ready for inspection. Everyone at works keeps laughing at my regular arguments I have with my contractor. The common comment is "you get what you pay for."
About two weeks ago, the contractor hired a sub-contractor to install an HVAC system into the house. In total the workers spent about five days installing the ducting in the house. Both myself and my Dad spoke to the boss and ensured they installed everything to our drawings. The most important thing was that we only wanted the ducting to be lower than the ceiling in two locations. In all other locations the ducting was to be located within the joists, hidden above the ceiling. The company is supposed to be putting the new units on the roof today or tomorrow. In order to do so the will be reinforcing the roof with iron rods. I have been pushing the Contractor to get these units installed ASAP, so we can call the inspector's to come and inspect everything.
During this time I had been working on installing the alarm system and wire distribution system. Both are now complete, but I still have to install the TV/Internet/Phone wire and will also install some more speaker wires for a surround sound system.
The Contractor's goal is to finish the framing, electrical, plumbing and HVAC inspections this week and possibly early next week. I am hoping for the best, which is he actually passes everything and we can start putting in drywall sometime late next week. It is very possible though that he will fail some (for reasons I don't feel like writing), and will need to address those required corrections. I have my fingers crossed!

Wednesday, October 1, 2008

Exterior wall complete, now electrical and plumbing.

The past two weeks have really gone by quickly.  During that time the contractor was mainly focused on building a new front wall.  To do so they had to first build a temporary wood wall inside the house.  With the temp wall in place they delivered a dumpster and tore down the old wall in one day.  The next two days the contractor built the new wall with 2x4s.  We had a few issues getting the windows framed where we wanted them, but after a few minor arguments my Dad helped center the first floor window and ensured the new look was symmetrical.  Another feature we requested was to expand the front door from 32inches to 36 inches, 4 inches can really help when moving furniture in. 

  

I was pleased on the fourth day when an expert brick layer showed up for work.  I was a little worried that the contractors general laborers were going to do the work, but instead they just mixed mortar and carried the bricks to the expert.  Overall the construction of the wall went fairly fast.  As they were constructing it, my Dad and I suggested they make two lines of brick come out of the wall a little under the windows and that they place the bricks vertical above the windows.  These two features definitely made the wall more original and to the theme of other rowhouses on the street.

Well my Dad unfortunately had to leave this last week.  He ended up spending about five weeks here in total.  I still can't believe it went so fast.  His last few weeks he worked on a wide variety of important projects that were not part of the contract.  His jobs included fixing leaks in the roof, installing a garage door, installing a new vinyl fence, installing retaining stars on the rear exterior wall, additional framing and a few other jobs.   Each Saturday I helped him for a full day, but other than that he did it all by himself, I was/am very thankful.

 

As soon the contractor finished with the walls, his guys went right back inside and have been trying to finish the electrical and plumbing work.  Their goal is to try and finish both these items by this weekend so they can be paid another big chunk of cash.  All my remodeling costs are financed by a Wells Fargo loan.  So in order for the contractor to get paid, he must complete a large portion of work, ask the bank for a inspection, and based on that inspection he receives a portion of the total renovation loan.